Infrastructure Projects
Overview
Launched in November 2023 by County Administrator Joy Andrews, the Infrastructure Delivery Team was created to accelerate the delivery of critical infrastructure projects for the St. Johns County community. This cross-functional team brings together key staff from more than eight County departments, along with partners from the St. Johns County Sheriff’s Office and the St. Johns County School District, to drive collaboration, innovation, and strategic use of resources.
The team oversees more than 100 active projects—representing over $450 million in funding from sources including developer contributions, impact fees, transportation trust funds, federal and state appropriations, and grants. Focused on improving efficiency and delivering timely results, the Infrastructure Delivery Team is committed to serving the growing needs of our community. These projects include transportation, parks, water and wastewater, public facilities, libraries, and other construction initiatives that improve the quality of life for the community.
This webpage is part of our commitment to transparency. Here, residents can find regular updates on project timelines, funding sources, and the progress being made across the county.
Abbreviations Glossary
- ACOE: Army Corps of Engineers
- BCC: Board of County Commissioners
- CMAR: Construction Management at Risk
- GMP: Guaranteed Maximum Price
- TBD: To be determined
Projects as of March 24, 2025
Construction Services
St. Johns County Sheriff’s Office Administration
- Current Phase
Design & CMAR
In negotiations - Expected Completion
End of 2027
Regional Parks Sportsplex
- Current Phase
GMP
Tentative BCC Meeting April 15, 2025 - Expected Completion
To be determined
Central Regional Park
- Current Phase
GMP
Tentative BCC Meeting April 15, 2025 - Expected Completion
To be determined
Northeast Regional Park
- Current Phase
Civil Work GMP
Tentative BCC Meeting October 17, 2025 - Expected Completion
To be determined
Davis Park
- Current Phase
Reviewing Quote from Design Consultant
Finalizing project scope to align with budget - Expected Completion
To be determined
North Beach Park
- Current Phase
Pending - Expected Completion
To be determined
Florida Emergency Response & Preparedness Complex
- Current Phase
Pending - Expected Completion
To be determined
Public Works
County Road 210 Widening I-95 to US1
- Current Phase
Design & CMAR in negotiations - Expected Completion
End of 2027
County Road 210 Widening Greenbriar to Cimaronne
- Current Phase
Major traffic flip in March - Expected Completion
May 2026
IGP & SR 16 Improvements
- Current Phase
Phase 1 contract approved March 4, 2025 - Expected Completion
Aug 2025
County Road (CR) 2209 (Central) From CR 210 to CR 208
- Current Phase:
Working with OCA regarding Pond site - Expected Completion:
Dec 2025
Parks and Recreation
St. Johns County Fishing Pier
- Current Phase
Award on BCC Meeting Agenda April 1, 2025
ACOE Permit still needed - Expected Completion
To be determined
Field of Dreams
- Current Phase
Bids due on March 19 - Expected Completion
To be determined
Utilities
Watson Road Closures
- Current Phase
Currently ahead of schedule - Expected Completion
To be determined
North Beach Utility
- Current Phase
Porpoise Point requesting emergency connect. - Expected Completion
To be determined
Capital Improvement Project Dashboards
For a full list of projects, including detailed information on project status, timelines, and funding, visit the Capital Improvement Project Dashboards.